Latambusiness.org ·Short Read·September 21, 2026·Updated October 14

AI Data Centers in Latin America, Explained

The region’s four biggest markets grew 41.3% in a year. One city accounts for nearly all of it. And of the 87 major AI data centers independently verified worldwide, not one is in Latin America.

CBRE’s Q1 2026 figures put operational inventory across Latin America’s four largest data center markets at 1,045.0 MW, up 41.3% year over year — the fastest inventory growth of any region on earth, ahead of North America at 33%.

Then you break it apart.

MarketInventoryYoYNet absorptionVacancy
São Paulo536.7 MW+8.9%39.2 MW9.6%
Querétaro298.2 MW+450.2%213.0 MW10.6%
Santiago165.8 MW+12%17.4 MW3.3%
Bogotá44.3 MWflat1.1 MW18.7%

The regional boom is one city. Querétaro grew 450.2% and took 213 of the region’s 270.7 MW of net absorption — 79% of everything leased across four countries — on the back of a small number of hyperscale and AI deployments. São Paulo, the market everyone means when they say “Latin American data centers,” grew 8.9%. Bogotá didn’t move at all: 44.3 MW, 1.1 MW absorbed, and CBRE attributes what demand exists to domestic enterprise rather than hyperscale.

“Latin America is booming” and “Querétaro is booming” are not the same sentence, and only one of them is true.

What’s being built now is different in kind from what’s operating now. Four announcements this year, all with real money behind them:

  • Ascenty (Digital Realty / Brookfield) announced on 28 May the signing of 150 MW of new hyperscale agreements driving US$1.2 billion across four new data centers in the São Paulo region. The anchor is Sumaré 3 — 90 MW initial with another 90 MW of expansion, 48,000 m², direct-to-chip liquid cooling and a closed-loop architecture. The 150 MW is fully pre-leased long term and equals more than 40% of all capacity Ascenty has built in its 15-year history. Initial delivery of Sumaré 3: second half of 2027.
  • ODATA (Aligned Data Centers) announced on 17 September a US$630 million first-phase investment to deploy DeltaFlow~ liquid cooling at SP04 in Brazil and QR03 in Mexico, with phase-one installation and testing already underway. The system is engineered to require zero water for operational cooling, recirculating deionized coolant in a closed secondary loop. The units are being manufactured at Munters’ plant in Araucária, Paraná — with Chile and Colombia named as upcoming destinations.
  • Equinix opened SP6 in Santana de Parnaíba on 16 April, a US$114 million facility built for high AI density and liquid cooling. It is Equinix’s sixth in São Paulo and ninth in Brazil.
  • Telxius opened a carrier-neutral, AI-ready Landing Gateway & Edge Data Center in Cancún on 3 September — Tier III, N+1/2N — as the landing point for the Tikal submarine cable to Boca Raton. Tikal is scheduled for H1 2027 at an estimated initial 380 Tbps on its main trunk. The facility also opens an alternative terrestrial route to Querétaro.

Note the dates. The AI-specific capacity and the connectivity to feed it both land in 2027. What CBRE counted in Q1 2026 is the previous generation of buildout. The AI wave in Latin America is contracted, financed and under construction — it is not yet operational.

Added 28 September 2026. Every operator named above is foreign-controlled, and two of the largest platforms in the table below changed ultimate owner in 2026. That is not a footnote to the buildout — it decides who can commit to Redata’s fifteen-year conditions and who will be your counterparty’s owner when a ten-year contract matures.

OperatorUltimate ownerCapital from
ScalaDigitalBridge — owned by SoftBank Group since 30 Sep 2026US → Japan
AscentyDigital Realty + Brookfield InfrastructureUS + Canada
EquinixEquinix Inc. (Nasdaq)US
ODATAAligned — AIP, MGX, BlackRock GIPUS + Abu Dhabi
CirionStonepeakUS
KIOI Squared CapitalUS
EleaPiemonteBrazil
TectoV.tal — BTG Pactual, GIC, CPPBrazil + Singapore + Canada
GtdGtd Grupo Teleductos (Chile, founded 1979); its data center arm, Gtdata, 49% InfraCorp (Grupo Romero) since Jan 2026Chile + Peru

Two transactions did most of that work, together worth roughly US$44 billion of enterprise value, with no Latin American buyer at either table.

ODATA moved in July 2026. Macquarie Asset Management, which had owned Aligned Data Centers since 2018, sold the platform at an enterprise value of about US$40 billion — the largest data center transaction on record — to a consortium of the AI Infrastructure Partnership, MGX, the Abu Dhabi state-backed investor, and BlackRock’s Global Infrastructure Partners. Aligned had acquired ODATA in 2023, so the Brazilian, Mexican, Chilean and Colombian facilities were inside the perimeter. The US$630 million DeltaFlow~ programme described above is now being delivered by a company nine weeks into new ownership.

Scala’s sponsor changed hands on 30 September. SoftBank Group agreed on 29 December 2025 to acquire DigitalBridge at roughly US$4.0 billion enterprise value, US$16.00 per share in cash. It completed the purchase of all outstanding common stock on 30 September 2026 (US time), for approximately US$3.1 billion by SoftBank’s own count; DigitalBridge is now a controlled subsidiary of SoftBank, run as a separately managed platform under Marc Ganzi. SoftBank bought the manager, not the asset: DigitalBridge created Scala in April 2020 out of UOL Diveo’s data center assets and controls it as a portfolio company. DigitalBridge had separately been marketing Scala and, on the reporting, holding out for a better valuation — so the region’s largest platform, the one planning 4.75 GW at Eldorado do Sul, now answers to a new parent while the asset itself has, on that reporting, been on the market. The grid has not waited on the deal: in May 2026 ANEEL’s board unanimously denied Scala’s requests to preserve the access opinions for its Jundiaí campus and its AI City in Eldorado do Sul.

The pattern in the table is the finding: the bigger the building, the more foreign the owner. The locally controlled operators — Elea, Tecto, Gtd — are the smaller, regional ones, and Tecto’s own capital includes Singapore’s GIC and Canada’s CPP. Gtd brought in a partner too: on 29 January 2026 InfraCorp, part of Peru’s Grupo Romero, became owner of 49% of Gtdata Holdco, Gtd’s data center subsidiary, in a US$109.8 million transaction, mostly new capital. It is the one Latin American buyer in the table. KIO shows where the local path usually ends: founded in Mexico in 2002, principal shareholder Tresalia Capital, sold in 2021 to a US infrastructure manager. Mexican-built, US-owned.

None of this is an argument against foreign capital. Ascenty’s 150 MW of pre-leased capacity and ODATA’s cooling investment happened because those sponsors could write the cheques. But it reframes the sovereignty language attached to this buildout. A facility in São Paulo, owned by an Abu Dhabi and US consortium, hosting a US hyperscaler, running NVIDIA silicon, is Brazilian in exactly one respect: the jurisdiction the building stands in. That satisfies a data-residency rule. It is not what “sovereign AI” is usually taken to mean.

The practical consequence for anyone signing: infrastructure funds have defined lives. Macquarie held Aligned eight years; Stonepeak has held Cirion four. Diligence the sponsor as well as the site, and read the change-of-control clause before the SLA.

On 15 September 2026, Brazil enacted Law 15.504, creating Redata — a special tax regime for data center services. It suspends PIS/Pasep, Cofins, their import equivalents, IPI and the import duty (Imposto de Importação) on electronic components and ICT goods destined for a qualifying operator’s fixed assets. On imported GPUs and cooling plant, that is a very large number.

The coverage stopped at “Brazil cut data center taxes.” The conditions are the actual story. To qualify, an operator must commit cumulatively to all of the following:

  • Make at least 10% of the processing, storage and data-treatment capacity installed under the regime available to the Brazilian domestic market — explicitly barred from routing it to export or own-use where domestic demand exists.
  • Meet 100% of its electricity demand from renewable or low-emission sources, via supply contracts or self-generation.
  • Hold Water Usage Effectiveness at or below 0.05 L/kWh, measured annually.
  • Invest 2% of the value of goods bought domestically or imported under the benefit into Brazilian R&D and innovation, in partnership with accredited research institutions.
  • Publish an annual sustainability report on a public website disclosing WUE and energy sources.

Read the second and third conditions next to what ODATA, Ascenty and Equinix just announced. A WUE ceiling of 0.05 L/kWh is not reachable with conventional evaporative cooling. It is reachable with exactly the closed-loop, zero-water-draw liquid systems those three are installing right now. Brazil did not merely make AI infrastructure cheaper — it made a specific cooling architecture the condition of the discount, and handed the advantage to operators who had already committed to it.

The renewable-power condition cuts the other way. It obliges the operator to solve, contractually and at 100%, precisely the problem CBRE flags as São Paulo’s principal constraint.

“Power procurement complexity and grid reliability concerns in certain submarkets continue to create uncertainty for large-scale deployments.” — CBRE, on São Paulo, in the same report that shows Latin America leading the world in inventory growth.

Epoch AI maintains a public dataset of the world’s largest AI data centers, built from high-resolution satellite imagery, construction permits and public filings rather than from company announcements. As of its 21 September 2026 update it covers 87 sites totalling 13.2 GW of IT power.

Seventy-five are in the United States. Four in China, two in Norway, one each in Malaysia, the United Kingdom, Indonesia, Australia, Portugal and the United Arab Emirates.

None are in Latin America.

The scale gap is worth stating plainly. The largest single site Epoch tracks — Colossus 2 in Memphis — draws 946 MW. That one building is 91% of the combined operational inventory of São Paulo, Querétaro, Santiago and Bogotá. All four Latin American markets together hold under 8% of what those 87 verified AI sites hold.

The two figures measure different things — CBRE counts wholesale colocation inventory across all workloads, Epoch counts IT power at AI-specific facilities — and that distinction is the point rather than a caveat to it. Announced capacity, contracted capacity, capacity under construction and capacity drawing power are four different numbers, and the regional conversation routinely quotes the first while implying the fourth.

Demand is not the open question. Querétaro absorbed 213 MW in a quarter; Ascenty pre-leased 150 MW before breaking ground; Santiago sits at 3.3% vacancy with only 5.4 MW available. The open question is whether the physical and regulatory systems can deliver. CBRE names the constraint in each market, and they are not the same constraint:

  • São Paulo — power procurement complexity and grid reliability in certain submarkets; currency volatility creating contract risk for international operators.
  • Querétaro — grid capacity limits are already forcing developers to self-generate or negotiate directly with utilities, adding cost and execution risk. Growth has also outrun the local skilled-labor pool, which stretches construction timelines.
  • Santiago — water availability in the Greater Santiago basin has brought regulatory oversight of cooling water, requiring more efficient cooling. Chile’s small domestic economy leaves the market dependent on international hyperscale demand.
  • Bogotá — no meaningful hyperscale pipeline yet. The constraint is demand, not supply.

Rental rates tell you where the pressure sits. Querétaro clears at US$250–270 per kW/month against São Paulo’s US$130–190 — the fastest-growing market in the region is also the most expensive, by nearly double, in a country whose grid is the reason.

For anyone selling into this — power, cooling, switchgear, fiber, EPC, or the capital behind it — three things follow.

The qualifying criteria are the specification. Redata converted Brazilian sustainability policy into a procurement requirement with a number attached. A vendor who can evidence WUE at or below 0.05 L/kWh and a 100%-renewable supply structure is not making a sustainability pitch in Brazil; they are making a tax-eligibility pitch. Chile is arriving at a similar place from the opposite direction, through water regulation rather than tax incentive.

Mexico and Brazil are different businesses. Querétaro is a grid-constrained, labor-constrained, high-rent market where the binding problem is getting electrons and electricians to a site. São Paulo is a mature, competitively priced market where the binding problem is contractual: power procurement and currency. Selling the same proposition into both is how deals stall.

Verify the number before you underwrite it. Telxius’s own Tikal product page still lists 190 Tbps of initial capacity while its September press release says 380 Tbps on the main trunk. That is a minor discrepancy on a real project by a serious operator — and it is exactly the class of thing that gets copied into an investment memo unchecked.

The demand signal is real and it is not in dispute. What is in dispute is delivery. Latin America has contracted more AI infrastructure this year than it has ever built, on grids that CBRE says are already the constraint, under rules Brazil wrote three weeks ago. The region has until 2027 to prove the difference between a signed contract and a running rack.

Franco Calderón · Latambusiness.org

Selling Into The LatAm Data Center Buildout?
Know Which Grid Can Carry You.

One market absorbed 213 MW in a quarter and can’t power the next one without self-generation. Another just made a water-efficiency number the price of the tax break. Thirty minutes on which markets, which counterparties, and which permits actually clear.

Book a Call
Primary sources read directly for this piece: CBRE, “Global Data Center Trends 2026” — Latin America inventory, vacancy, net absorption, rental rate and featured-market sections, Q1 2026 data · Ascenty, “Ascenty Secures 150 Megawatts of New AI Contracts with Leading Global Hyperscalers” (28 May 2026) · ODATA, “ODATA Brings Next-Generation Cooling to Latin America with DeltaFlow~™ Liquid Cooling Technology” (17 Sep 2026) · Equinix Newsroom, SP6 inauguration (16 Apr 2026) · Telxius, “Telxius Boosts Caribbean Connectivity and expands Mexican footprint with New Cancun Landing Gateway & Edge Data Center” (3 Sep 2026) and Telxius Tikal cable page · Presidência da República / Planalto, Lei nº 15.504, de 15 de setembro de 2026, full text including Arts. 11-A, 11-B and 11-C (DOU 15.9.2026, edição extra) · Epoch AI, “AI Data Centers” dataset and accompanying CSV, updated 21 Sep 2026 (site-by-site country counts computed directly from the published dataset).

Ownership section added 28 September 2026. Company primaries: Ascenty’s own investors page, which states it “is supported by Digital Realty… and Brookfield Infrastructure” · Stonepeak’s completion release for the Lumen Latin America acquisition (1 August 2022), which created Cirion · DigitalBridge’s investor-relations release and SEC Form 8-K on the SoftBank transaction (29 December 2025; ~US$4.0bn, US$16.00 per share, closing expected H2 2026) · SoftBank Group, “Completion of Acquisition of DigitalBridge” (30 Sep 2026; ~US$3.1bn) · Gtd Grupo Teleductos, Análisis Razonado as of 30 June 2026 (Gtdata Holdco transaction with Cubo BidCo SpA, managed by InfraCorp, Grupo Romero) · ANEEL, Despacho 1.813/2026 (Scala), via ANEEL’s board decisions open dataset · Macquarie Asset Management’s announcements on the Aligned Data Centers sale (~US$40bn enterprise value, closed July 2026). Reported via trade and financial press, and labelled as such: the composition of the Aligned buying consortium (AIP, MGX, BlackRock GIP); DigitalBridge’s creation of Scala in April 2020 from UOL Diveo assets and its reported search for a better valuation on a Scala sale; I Squared Capital’s 2021 acquisition of KIO from Tresalia Capital; Piemonte’s backing of Elea; BTG Pactual’s control of V.tal with GIC and CPP Investments in Tecto’s funding; and the Data Centre Magazine ranking of the region’s largest operators (11 March 2026), used for the constituent list rather than for any ownership claim. Gtd’s own shareholder page is script-rendered and returned no register, so no claim is made about the parent’s cap table; the Gtdata stake comes from Gtd’s own Análisis Razonado. Corrections, 14 October 2026: the SoftBank–DigitalBridge transaction, previously shown as pending, closed on 30 September; the Gtd row now shows InfraCorp’s 49% of Gtdata, which closed on 29 January 2026 and was missing from the 28 September update; “while this piece was live” was wrong (the Aligned sale closed in July, before publication); and “building 4.75 GW” now reads “planning”, with ANEEL’s May ruling added.

Noted discrepancy: Telxius’s 3 September 2026 press release states an estimated initial 380 Tbps on Tikal’s main trunk; the Tikal cable page on the same site still states 190 Tbps. Both are Telxius primary sources. The more recent figure is used above and the conflict is disclosed rather than resolved.

Written with AI assistance. Every figure in this piece was checked against the primary sources named above, each of which was directly retrieved; the ownership details reported via trade and financial press are labelled as such above.